top of page

June Construction Update

  • 8 hours ago
  • 2 min read

Old Infrastructure Comes Down as New Systems Take Shape

With major demolition advancing and new infrastructure steadily taking shape, June offered one of the clearest views yet of the plant's early transition from a 100-year-old facility to a modern treatment system. As overheard by one worker on site, "You can really feel the progress around here now.”


Sand Filter Demolition Reaches Major Milestones

Demolition activity accelerated throughout June. Most of Filters 9 and 10  were demolished, and work also advanced on demolishing Filters 7 and 8. These filters date from 1925.


Large excavators weighing approximately 74 metric tons are being used to break apart and move materials.
Large excavators weighing approximately 74 metric tons are being used to break apart and move materials.

Filters 9 and 10 undergoing demolition in June.
Filters 9 and 10 undergoing demolition in June.

Crews continue to remove concrete, sand, and metal materials in carefully separated streams. Concrete debris is hauled off-site for future crushing and reuse, while metal components are transported for recycling.


As demolition progresses, crews continue removing not only thousands of cubic yards of sand that had filtered our water for decades, but also access structures and support features. All of this must be cleared from the site to make way for the new plant.


Piles of filter sand at the site.
Piles of filter sand at the site.

Concrete Pumping, Pouring, and Placing

At the same time, construction of major components of the new plant continues. Crews spent much of June installing rebar, building forms, and placing concrete to encase new 60-inch and 72-inch water mains that will carry raw water across the campus to the new WTP. Large concrete pump trucks and specialized crews worked through a series of carefully coordinated concrete pours, with quality-control testing performed on every batch to ensure the new infrastructure meets long-term performance standards.


A concrete truck pumps concrete for the encasement of new 60-inch and 72-inch water mains near the Backwash Facility.
A concrete truck pumps concrete for the encasement of new 60-inch and 72-inch water mains near the Backwash Facility.

A bend in the new water main alignment was completed. Pipe sections that had been installed earlier this spring were fully welded and prepared for backfilling, marking significant progress in establishing the backbone of the future treatment system.


Pipes installed last month are now welded and ready for encasement.
Pipes installed last month are now welded and ready for encasement.

The Precision Behind the Progress

Behind every visible change is planning and precision. Survey crews use GPS-based positioning systems to ensure new infrastructure is installed where designers intended, while contractors coordinate the moving parts of demolition, excavation, concrete placement, material recycling, and environmental controls across the active construction site.


Standing next to a hydraulic pneumatic rock hammer (“hoe ram”), a construction worker uses a GPS positioning system to lay out the centerline and depth of piping, ensuring placement according to project specifications. This location shows the pipe path heading from the recently completed Energy Dissipating Valve Facility towards the Backwash Facility in the background.
Standing next to a hydraulic pneumatic rock hammer (“hoe ram”), a construction worker uses a GPS positioning system to lay out the centerline and depth of piping, ensuring placement according to project specifications. This location shows the pipe path heading from the recently completed Energy Dissipating Valve Facility towards the Backwash Facility in the background.

60” and 70” pipeline install and bend around the Backwash Facility
60” and 70” pipeline install and bend around the Backwash Facility

 
 
New West Parish Water Treatment Plant

Main Number: 413-452-1300

Customer Service: 413-452-1393

Springfield, MA, USA

Springfield Water and Sewer Commission Logo
bottom of page