October Construction Update

1 hour ago
2 min read

October brought steady progress across several areas of the project, with crews continuing underground piping work, concrete encasement, rock removal, and restoration.


Underground piping takes shape

Work continued in the new building footprint, where crews are installing two 30-inch pipes. These are among the deepest pipes in this area, so their installation is an important early step in building the site from the ground up. Once the lower piping is concrete-encased and backfilled, crews can begin working upward to install additional piping. 


These two pipes are among the deepest to be laid beneath the new plant’s future pipe gallery. 
These two pipes are among the deepest to be laid beneath the new plant’s future pipe gallery. 

The progress is already visible. At the beginning of the month, sections of pipe could be seen staged alongside the excavation. By the end of October, those sections had been installed in the trench. 


The staged sections of pipe alongside the excavation site at the beginning of October.  
The staged sections of pipe alongside the excavation site at the beginning of October.  


Concrete encasement continues

Crews also made progress on the large 60- and 72-inch raw water mains being installed across the campus to the site of the new plant. Portions of the piping received concrete encasement during October, providing protection and support before the area can be backfilled and work continues above it. 


Concrete encasement of raw water pipes continues. This is a segment located behind the Backwash Facility.
Concrete encasement of raw water pipes continues. This is a segment located behind the Backwash Facility.

Welding work continued as well, preparing additional sections of pipe as construction moves forward. 


Welders continued to work hard this month on the 60- and 72-inch pipes. 
Welders continued to work hard this month on the 60- and 72-inch pipes. 

Making way for the 60-inch transmission main

Farther up the site, crews continued removing rock to make way for the new 60-inch transmission main. Excavators worked through the rock as construction progressed uphill and past the field house. 


Two machines work together to remove rock against a backdrop of autumn leaves at the beginning of the month. 
Two machines work together to remove rock against a backdrop of autumn leaves at the beginning of the month. 

Rock removal can be a slow process, but it is necessary to establish the route for the new main and prepare the area for future installation. 


Restoring completed work areas

October also brought visible restoration in areas where construction had progressed far enough for surfaces to be put back in place. Near Gate 4, crews repaved the driveway, placed topsoil, and hydroseeded the surrounding area to reestablish grass. 


An area where raw water transmission mains have already been installed and encased, at the beginning of the month, before topsoil was placed. 
An area where raw water transmission mains have already been installed and encased, at the beginning of the month, before topsoil was placed. 

A hydroseeded area atop newly installed raw water transmission mains, at the end of the month. 
A hydroseeded area atop newly installed raw water transmission mains, at the end of the month. 

Together, these activities show the project moving at several simultaneous stages, from excavation and pipe installation to concrete encasement and restoration. With plenty more construction ahead, each month adds another layer to the transformation of the site. 


Workers check the plans as the project moves into its next phase.
Workers check the plans as the project moves into its next phase.

An aerial shot of the Backwash Facility, and the pipeline installation and restoration work around it, October 2026.
An aerial shot of the Backwash Facility, and the pipeline installation and restoration work around it, October 2026.

An aerial view of the existing West Parish Filters Water Treatment Plant (at left) and the site of the new water plant. The deepest pipes that will be installed for the project are seen in the center of the excavated area.
An aerial view of the existing West Parish Filters Water Treatment Plant (at left) and the site of the new water plant. The deepest pipes that will be installed for the project are seen in the center of the excavated area.

 
 
New West Parish Water Treatment Plant

Main Number: 413-452-1300

Customer Service: 413-452-1393

Springfield, MA, USA

Springfield Water and Sewer Commission Logo
bottom of page